Temporary Steel Deck Works at Sungei Punggol and PCN
Q4 2023 to Q3 2024
Partial Park Connector Network Temporary Closure (Tentative End Dec 2023 to Early 2024)
Viaduct Construction at Sungei Punggol and PCN
Q4 2023 to Q3 2025
Viaduct Construction Works at PCN Q4 2023 to Q3 2025
Staircase Diversion at Layar Station, Exit B Q4 2023 to Q3 2025
Temporary Lane Closure along Sengkang West Avenue from Q4 2023 to Q2 2025. The lane closure will be conducted in 2 phases. •Phase 1: Q4 2023 to Q2 2024 for viaduct pier construction works. •Phase 2: Q1 2025 to Q2 2025 for viaduct segment launching works.
Viaduct Construction
Q4 2023 to Q3 2025 SPDE Construction
(On-going till December 2026)
At Sengkang Depot Roof
Bus Stop Relocation (BS 67321) Q4 2023 to Q1 2025
Lane Reduction along Sengkang Avenue Q4 2023 to Q1 2025
Lane Reduction along HDB Driveway Q1 2024 to Q2 2024
Viaduct Construction Q2 2024 to Q3 2025
Viaduct Construction Q4 2023 to Q3 2025
Upcoming Enhancement Works at Sengkang Town Centre (STC) Station Platforms
Q1 2024 to Q3 2024 Anchorvale Lane Road Closure for Utility and Drain Diversion Works along Sengkang East Avenue 23 July 2023 to Q1 2024
Re-Opening of Anchorvale Lane with Lane Reduction Q1 2024 to Q1 2025
Viaduct Construction Q2 2024 to Q3 2025
Viaduct Construction Q4 2023 to Q3 2025
Viaduct Construction Q4 2023 to Q3 2025
Installation of Temporary Protection Enclosure on existing LRT Viaduct
Mid Dec 2023 to Q3 2024 Temporary Lane Closure
Legend:
Pilling Works
Temporary Steel Deck
New Reception Tracks
Temporary Road Closure